Project objective:  

Kings Heath Demolition Ltd have successfully completed a large complex contract at the Former Wolseley Distribution hub at Spa Park, Leamington for our valued client. 
 
 

 Method:  

The contract involved the dismantling of a link bridge serving the two warehouses. A full strip out to the internal offices and dismantling/full demolition of 6,000m2 of internal mezzanine floors and equipment was also carried out. As part of the contract we also removed some external buildings/staircases and completely removed the external canopies and gable walls. 
 
 

 Solution:  

The contract was completed ahead of time and on budget to the satisfaction of our client. 
 