The contract involved the following works:
Removal of 10,000m2 of roof coverings
Dismantling four overhead cranes and acsssociated rails
Demolition of various outbuildings
Removal of concrete hardstandings
Removal of internal racking systems
Removal of the building slab
On-site crushing of concrete
All site-won concrete was crushed on site and reused in the redevelopment, a huge environmental and cost saving.
Despite prolonged inclement weather during the project, works were completed within the agreed program.